top of page

more case studies

Midland Interchange, WA

In 2012 over 3500m² of Pour On Gravel Binder was used to stablise a decorative gravel finish to a newly developed landscape feature at the busy interchange in Midland, WA.

The finish required was to utilise attractive, locally sourced gravel, but to offer a low maintenance solution which maintained full porosity.

Product Name: Pour On Gravel Binder

Area: 3500m²

Depth of lay: 30-40mm

Midland Interchange, WA

Pour On

The process of installation is as simple as it seems. A 20ltr bucket is prepared by drilling 1-2mm sized holes through the bottom of the bucket and simply walking the resin over the loose gravel ensuring an even application.

This process is usually completed in two or three layers and can be smoothed out with a straight edge or even a steel trowel immediatly after the first resin application. Alternatively a rougher finish can be achieve as was required on this project to discourage foot, bicycle and skateboard trafficking.